BESS Weekly: GridStor's fifth deal in 18 months

GridStor acquired the 199MW/796MWh Birdseye project in Colorado, its fifth deal in 18 months.

GridStor acquired the 199MW/796MWh Birdseye project in Colorado, its fifth deal in 18 months. The Goldman-backed platform is now past 530MW operating or under construction with a 3GW pipeline.

Ford Energy signed a five-year framework with EDF Power Solutions for up to 20GWh of LFP DC Block systems, built in Glendale, Kentucky.

The California Energy Commission approved Clearway's 400MW/3,200MWh BESS in Alameda County, the third project cleared under AB 205 fast-track permitting.