FERC approved MISO's plan to clear 35GW stuck in its 2022 interconnection cycle, 18 months earlier than it would otherwise have moved.
MISO won FERC approval on Friday to clear its 2022 interconnection cycle: 35GW that would otherwise have slipped 18 months and stalled three later cycles. Across all four cycles the queue holds nearly 600 projects and 125GW, 25GW of it batteries.
The signal The fix is a penalty-free exit before Decision Point II, a 50% network-upgrade cost trigger instead of 35%, and one restudy in DPP-III. MISO is clearing its backlog while PJM buyers wait on projects that can reach a bid.
Hiring One restudy means one chance to get the numbers right. Developers holding MISO storage positions need Interconnection Engineers who can clear DPP-III in a single pass, Development Managers who can rank which sites fund upgrades, and Transmission Engineers who can price against a 50% trigger.